RSMeans is a construction cost database published by Gordian. It lists unit costs for materials, labor and equipment, along with crew sizes and productivity, and it adjusts those costs for more than 970 locations across North America. We price every estimate against current RSMeans data combined with local, zip-code-based material and labor pricing.

This post explains what's inside an RSMeans cost line, how the City Cost Index turns a national figure into a local one, and where published data needs a person's judgment. It also walks through how we use it on a real estimate. If you've seen "priced against RSMeans" on a bid and wondered what it means, this is the long answer.

What RSMeans data is

RSMeans has been a reference point for US construction pricing for decades, and Gordian now publishes it, mainly through RSMeans Data Online (Gordian). According to Gordian, the online data:

  • Gets automatic quarterly updates to all cost elements
  • Can be localized to more than 970 locations across North America
  • Supports estimates built from unit costs, assemblies or square-foot models
  • Breaks each price into material, labor, equipment and productivity

Owners, architects, government agencies and contractors all use it. Part of its value is that it's a shared reference. When two parties both point to the same published cost for a line item, a pricing disagreement turns into a discussion about the specifics of this project instead.

What's inside an RSMeans unit cost line

A unit cost line describes one piece of work, such as placing concrete in a slab or hanging a sheet of drywall, and prices it per unit of measure. The columns in a typical line:

ColumnWhat it tells you
CrewThe standard crew for the task, such as a carpenter and a laborer, or a crew with a concrete pump
Daily outputHow many units that crew is expected to install in an eight-hour day
Labor-hoursLabor hours per unit, which follows from the crew size and daily output
UnitThe unit of measure: CY, SF, LF, EA and so on
Bare costsMaterial, labor and equipment cost per unit, before the installing contractor's overhead and profit
Total including O&PThe same work with the installing contractor's overhead and profit added

The difference between bare costs and the total including O&P matters a lot in practice. A general contractor pricing work its own crews will do starts from bare costs and adds its own overhead and markup. When the same work is subcontracted, the sub's overhead and profit are already in the price, so the total including O&P is the closer comparison.

The crew and productivity columns matter just as much. They're what turn a quantity into labor hours. If a crew installs fewer units a day than the standard because of tight access, work at height or a lot of small pieces, the labor cost per unit goes up, and an estimator has to recognize when that applies.

How the City Cost Index localizes national costs

RSMeans national figures are based on an average of 30 major US cities, which is set to an index of 100. Each location gets its own index number for material and for installation. A city with an index of 110 runs about 10% above the national average, and one with an index of 90 runs about 10% below it (RSMeans City Cost Index).

The arithmetic is simple:

Local cost = national average cost × (city index ÷ 100)

As an illustration only, if a line item costs $1,000 at the national average and the local index is 92, the localized cost is $1,000 × 0.92 = $920. In practice, material and installation each have their own index, so the two parts of a line item are adjusted separately.

Location effects are large. In the Census Bureau's 2025 data on new contractor-built homes, the median contract price per square foot (excluding land) ranged from $157.30 in the South to $194.09 in the Midwest (US Census Bureau). An estimate priced at a national average would be wrong in both regions, in opposite directions.

Unit, assembly and square-foot costs

RSMeans data comes in three levels of detail, and each one fits a different stage of design:

LevelWhat it pricesFits best whenTypical AACE estimate class
Square-foot modelsA whole building type per square footOnly the size and use are knownClass 5
AssembliesSystems such as a wall type, a roof or a footingSchematic design, systems chosen but not detailedClass 4
Unit costsIndividual items of work measured from drawingsDetailed drawings and a full takeoffClasses 3 to 1

The estimate classes come from AACE International's Recommended Practice 56R-08, which ties the estimating method to how complete the design is (AACE 56R-08). A square-foot estimate can be useful for a go or no-go decision, but AACE puts its expected accuracy as wide as -30% to +50%. A detailed unit-cost estimate on complete drawings narrows that to about -3% to +10%.

For bid-ready work, we price at the unit-cost level. For early budgets, our preliminary estimate service works at the square-foot and assembly level, and our free construction cost calculator gives a ballpark range from published averages.

How we price an estimate with RSMeans data

Here's the sequence on a typical full cost estimate:

  1. Measure the quantities. We take off every item from your plan set, trade by trade, and organize it by CSI division. If you only need quantities, this is where a construction takeoff stops.
  2. Match each quantity to a cost line. Each measured item gets a unit cost referenced to current RSMeans data, with the material, labor and equipment parts kept separate.
  3. Localize the pricing. We price material and labor for your project's zip code instead of using a national average.
  4. Build the full number. Equipment, overhead and markup are added, and the result stays organized by CSI division so it can be compared with other bids line by line.
  5. Senior review. A senior estimator checks quantities, pricing and scope before the estimate leaves our office.
  6. Deliver in your format. You get the estimate in the software or file format your team already uses, whether that's AccuBid, PlanSwift, Bluebeam, a spreadsheet or something else. See the software we work in.

Most estimates are delivered in 24 to 72 hours, and the price is confirmed up front before any work starts.

Where published cost data needs judgment

RSMeans gives a strong starting point, but it doesn't know your project. These are the places where a published number shouldn't be taken at face value:

  • Fast-moving material prices. Quarterly updates are frequent for a database, but lumber, copper and steel can move faster than that. When a material is volatile, current local pricing matters more than the last published figure.
  • Specialty and proprietary items. Custom equipment, specialty finishes and products from a single manufacturer often need a supplier quote.
  • Local labor conditions. Union and open-shop rates, prevailing wage requirements and how busy local trades are all change real labor costs.
  • Productivity on this specific job. Standard daily outputs assume typical conditions. Occupied buildings, phased work and tight sites usually run slower.
  • Your own history. A contractor's records from finished jobs reflect its own crews and suppliers, and they're often the best check on any published number.
SourceStrengthsLimits
RSMeans published dataConsistent, documented, localized, updated quarterly, recognized by owners and agenciesNational method, standard productivity, can trail fast price changes
Your historical costsReflects your own crews, suppliers and marketsOnly as good as your records, and thin for work you rarely do
Current supplier and sub quotesThe real price for this project todayTakes time to collect, and scopes vary from quote to quote

Good estimates use all three. Published data gives a consistent, defensible baseline, and current local pricing and project knowledge adjust it to the job you're actually bidding.

Frequently asked questions

RSMeans Data Online is Gordian's web-based version of the RSMeans construction cost database. It provides unit, assembly and square-foot costs with quarterly updates and location factors for more than 970 North American locations.